SAN
JOSE UNIFIED SCHOOL DISTRICT San José, California July 11, 2002 (Board Meeting August 7, 2002) SUBJECT:
Amend Measure F Expenditure Plan
(ACTION) REQUESTED ACTION:
That the Board of Education adopt an interim plan for Measure
F expenditures for the 2003-2004 Fiscal Year. BACKGROUND:
Whereas the Measure F Implementation Plan has not been finalized
and it is imperative to proceed with the design phase of certain projects.
So as to not jeopardize the construction schedule, the following
procedure has been developed for obtaining approval to proceed with
individual projects until the Implementation Plan is adopted by the
Board of Education. I. Review
the detailed planning document for Measure F with the CBOC (scheduled
for review on 9/16/02). II. Prior
to board adoption of the Measure F Implementation Plan, limit further
expenditures as follows: A. No
more than a total of 5% of voter authorization or $21,429,000 (excluding
the new elementary school at Empire Gardens). B. Within
that total, expenditures for Measure F funds will be allowed only for
the District’s highest facility priorities as follows: Priority 1: Health
and Safety Priority 2: Building
Protection Priority 3: Educational
Program It is recommended that no expenditures be approved for
the priority 3 Category unless one or more of the following conditions
exist: 1. The delay
of the project would have a significant negative impact on the overall
construction schedule. 2. The delay
of the project would add cost (other than inflationary costs to the
project). 3. The delay
of the project would prevent the District from meeting obligations to
other funding agencies who are supporting the project. Leveraging partnerships
and state funding reduces the amount of district resources required
to support the facilities renovation and improvement.
C. All such
expenditures shall be brought to the CBOC for information and the Board
of Education for approval. D. Effective
November 21, 2002, no temporary funding, such as certificates of participation,
will be used to bridge temporary funding gaps for projects which are
candidates to be funded by Measure F monies prior to CBOC review and
Board approval of those projects.
Prepared by,
Gerald F. Matranga,
Associate Superintendent
Administrative Services
Approved by,
Linda T. Murray, Ph.D.
Superintendent of Schools GFM:lr |